Report week 34 · baseline week 48 of 261

Progress Curves

Cost-loaded baseline vs. earned value · data date 13 Aug 2026 · all values in SAR
Planned
13.48%
Baseline at data date
Earned
12.56%
10.43 M
Deviation
−0.92%
Actual − plan
SPI
0.932
Earned ÷ planned
Weeks remaining
213
to 12 Sep 2030
Forecast finish
30-Dec-2030
+109 days vs baseline

Overall Progress

Full baseline · 261 weeks · 18 Sep 2025 → 12 Sep 2030

Cumulative % of BAC

Near-Term View

16 weeks either side of the data date — where the weekly meeting lives

Deviation

Actual minus plan · green above baseline, red below

Discipline S-Curves

Each against its own budget, so a 5%-weighted phase is not flattened by a 50% one

Engineering

4,152,643 SAR · 5% of project

49.4%
−1.3%

Procurement

41,526,433 SAR · 50% of project

19.5%
−2.1%

Execution

33,221,148 SAR · 40% of project

0.9%
+0.4%

Close-out

4,152,645 SAR · 5% of project

0.0%
0.0%

Weekly Velocity

Last 20 recorded weeks — earned against what the baseline expected

The cumulative curve hides the recent trend. A project can sit behind overall while pulling back a little each week — or sit on plan while having stalled a month ago. These bars separate the two.

SPI Trend

Cumulative earned ÷ planned, week by week

Cumulative SPI moves slowly by construction, so the shape matters more than the level: a flat line means the gap is holding, a falling one means it is opening.

Weekly Progress

Last 16 recorded weeks, newest first · baseline week 48 is the data date

39 weeks recorded
WkWeek endingThis weekCumulativeDev.SPIEarned
PlanActualPlanActualSAR
4813 Aug 2026data date0.61%0.01%13.48%12.56%−0.92%0.93211,758
4706 Aug 20260.63%1.50%12.86%12.55%−0.32%0.9751,245,258
4630 Jul 20261.46%0.53%12.24%11.05%−1.19%0.903444,136
4523 Jul 20260.70%0.31%10.78%10.51%−0.26%0.975260,214
4416 Jul 20260.71%0.69%10.07%10.20%+0.13%1.013573,860
4309 Jul 20260.63%0.29%9.37%9.51%+0.14%1.015242,183
4202 Jul 20260.47%0.19%8.74%9.22%+0.48%1.054159,151
4125 Jun 20260.47%0.30%8.27%9.02%+0.76%1.091248,980
4018 Jun 20260.31%0.52%7.80%8.72%+0.92%1.118435,230
3911 Jun 20260.21%0.84%7.49%8.20%+0.71%1.094693,745
3804 Jun 20260.15%0.20%7.28%7.36%+0.08%1.011169,602
3728 May 20260.09%0.00%7.13%7.16%+0.03%1.0041,743
3621 May 20260.18%0.29%7.04%7.16%+0.12%1.017239,687
3514 May 20260.18%0.14%6.86%6.87%+0.01%1.001112,866
3407 May 20260.14%0.07%6.68%6.73%+0.05%1.00858,869
3330 Apr 20260.12%-0.09%6.54%6.66%+0.12%1.018-71,883

The two “this week” columns are differences of the cumulative ones, never entered separately, so a week can never disagree with the running total. Week 33 shows a negative actual: earned value was corrected downwards by 71,883 SAR as previously claimed progress was written back.

Discipline Summary

At data date 13 Aug 2026 · SAR

DisciplineBACWeightPlan cum.Earned cum.Plan %Actual %Dev.SPI
Engineering4,152,6435%2,102,0542,049,74550.62%49.36%−1.26%0.975
Procurement41,526,43350%8,936,3348,081,90121.52%19.46%−2.06%0.904
Execution33,221,14840%154,211299,3540.46%0.90%+0.44%1.941
Close-out4,152,6455%100.00%0.00%0.00%0.000
TOTAL PROJECT83,052,869100%11,192,60010,431,00013.48%12.56%−0.92%0.932