SPP-19/025-RR-001 Rev 1

Risk Register

Scored on the SASREF SP-029 risk assessment matrix — severity 1–5 against likelihood A–E, assessed before and after mitigation.
Total risks
16
Open
16
Actively managed
Inherent L4
3
Very high, before mitigation
Residual L3
2
High, after mitigation
Residual L2
14
Medium, after mitigation

Inherent Risk

Before mitigation

5R3R2
4R4, R5, R7, R8, R13R10, R16R1
3R9, R11, R12, R14R6, R15
2
1
ABCDE
↑ SeverityLikelihood →

Residual Risk

After mitigation

5R3
4R4, R7, R8, R13R2
3R5R1, R6, R9, R10, R14, R15, R16
2R11, R12
1
ABCDE
↑ SeverityLikelihood →

Register

Ordered by reference — R1 through R16, the way the document reads

16 risks
16 shown
#CategoryRisk / threatInherentResidualOwnerDueStatus
R14.1 Schedule / LDsDelay or extension of schedule, exposing the contract to liquidated damages4D · L43B · L2SASREF / alfanarPre-shutdownOPEN
R24.1 Schedule / LDsLimited shutdown window; scope not completed within the agreed outage5D · L44B · L3SASREF / alfanarPre-shutdownOPEN
R31.5 OperationLoss of power to running refinery loads during switching between sections5C · L45A · L3SASREF / alfanarPre-shutdownOPEN
R44.5 Startup / CommissioningFailure to start up the new switchgear on schedule4B · L34A · L2alfanarDesign / FAT stageOPEN
R52.2 IT requirementsFailure to integrate the new PMS with existing PMS/DCS and cybersecurity4B · L33A · L2SASREF / alfanarDesign stageOPEN
R64.4 ConstructionSite access, gate pass and permit constraints delaying mobilisation3D · L33B · L2SASREFPre-shutdownOPEN
R74.3 FabricationEngineering and material mismatch causing rework of cables and terminations4B · L34A · L2alfanarDesign / FAT stageOPEN
R84.2 ResourcesLoss of project knowledge and continuity through key personnel turnover4B · L34A · L2alfanarThroughoutOPEN
R91.1 HSE / Security / RegulatorySafety incident from overcrowding or work in live zones3C · L33B · L2alfanarShutdownOPEN
R103.6 ProcurementLate delivery of long-lead items — switchgear, protection relays, power cable4C · L33B · L2alfanarPre-shutdownOPEN
R111.2 QualityNCRs arising from poor-quality joints or terminations3C · L32B · L2alfanarConstructionOPEN
R124.4 ConstructionUnforeseen underground utilities on the fibre-optic cable route3C · L32B · L2alfanarConstructionOPEN
R133.1 Contract / ClaimsUncontrolled or late scope changes after contract award4B · L34A · L2SASREF / alfanarThroughoutOPEN
R141.3 Engineering / Performance GuaranteesDesign defects discovered after IFC drawings are released3C · L33B · L2alfanarDesign stageOPEN
R154.1 Schedule / LDsIdle resources and manpower from shutdown cancellation or rescheduling3D · L33B · L2SASREFPre-shutdownOPEN
R164.5 Startup / CommissioningPMS detailed design not completed in time to support the outage4C · L33B · L2alfanarDesign stageOPEN